INSTALLATION AND MAINTENANCE OF STIRRING TOOTH GRANULATOR

搅齿造粒机

Installation and test machine of Stirring Tooth Granulator:
1. The equipment should be installed on a level concrete foundation and fixed with anchor bolts.
2. Pay attention to the verticality between the main body and the horizontal when installing.
3. After installation, check whether the bolts in each part are loose and whether the door of the main engine is fastened. If so, please fasten it.
4. Configure the power cord and control switch according to the power of the equipment.
5. After the inspection is completed, a no-load test run is carried out, and the test run is normal and production can be started.

Maintenance of Stirring Tooth Granulator:
2. The newly installed wheel tyres are prone to loosening and must be checked frequently.
3. Pay attention to whether the various parts of the stirring tooth granulator work normally.
4. Pay attention to check the degree of wear of easily worn parts, and pay attention to replacing worn parts at any time.
5. On the plane of the bottom frame of the movable device, dust and other objects should be removed to prevent the movable bearing from moving on the bottom frame when the machine encounters unbreakable materials, which may cause serious accidents.
6. If the bearing oil temperature rises, stop the machine immediately and check the cause to eliminate it.
7. If the rotating gear is running, if there is an impact sound, stop and check it immediately and eliminate it.